Mains Changeover

Case Study – London College

Project: Mains Changeover

Date: November 2011

For this particular project, an out-of-hours mains change was required for a busy day care centre in a Stepney Community Centre, North London. For the sake of minimum disruption, the client requested that this project was completed in ONE night, so it was all hands to the deck, and several engineers later, we managed to remove all of the existing isolators, redundant containment and associated cabling as seen here in the 1st 2 pictures below…

… and installed 2 new 8-way 3phase distribution boards in their place, which involved re-wiring all of the existing circuits back to the new distribution boards within the 12 hour allotted time slot.

Upon completion, the new circuits were tested and the relevant certification handed over to the client.